Bioče–Petnjica road works halted as contract annex awaits signature

Reconstruction of the Bioče–Petnjica road has stopped while a contract annex with the Directorate for Transport awaits signature, a delay of more than a month that is holding up asphalt works. The project is valued at 11.7 million euros.

The approximately nine-kilometre section is significant for Petnjica and neighbouring Berane and Bijelo Polje. It is also important because it will provide Petnjica with a future connection to the motorway, Bemax engineer Irfan Alamerović said.

Expropriation has been resolved along 7.5 kilometres of the route. Workers are also dealing with unresolved expropriation and the relocation of existing installations, particularly a substation.

Work slowed after strong progress

Construction officially began in August last year. Bemax is the contractor and the Directorate for Transport is the investor.

About 100 workers were deployed while work was being carried out on 7.5 kilometres of the route. Activities were reduced during the last month because work could not continue.

Alamerović said progress had been extremely good and that the project was ahead of its schedule until a month ago. He said Bemax had completed everything possible under the basic contract.

Annex required for asphalt works

The annex will not complete the entire project, Alamerović said, but will cover a significant part of the work already started. The Transport Administration is responsible for signing it.

Alamerović said the Transport Administration was directly responsible for any further delay to asphalt works, as Bemax had been ready to carry them out for more than a month.