Fintel energija expects the Košava 2 wind farm to be fully operational during 2027, with planned capacity of up to 70 megawatts, the company said in its financial report. The project has secured all licences, while strategic partner Windey Energy Technology Group is due to invest in Fintel’s Serbian project development platform and help accelerate permit approvals.
Košava 2 is planned to have 19 wind turbines. Fintel’s report says its capacity has been increased to 70 megawatts, while the project is among the company’s most advanced developments.
“Among projects under way, Košava 2 is the most advanced after Kula 2, Kula 3 and Kula 4,” Fintel management wrote in the report. The company also produces electricity at the Kula, La Piccolina and Košava 1 wind farms and is developing solar projects.
MK-Fintel Wind said early last year that it had secured financing for the Košava wind farm expansion. The plan at that time was to raise capacity from 69 to 105 megawatts, an increase of 36 megawatts; NLB Bank described the financing as one of the largest individual financings carried out by its banking group in the local market, but did not disclose its value.
Fintel management expects loans to cover 80% to 90% of all planned investments, with the remainder financed through subordinated debt or the company’s cash flows. It expects the development of its wind and solar projects to support business growth.
Windey partnership covers projects and permitting
Fintel energija concluded a strategic partnership agreement with Windey Energy Technology Group in late September. The agreement provides for direct equity investment by Windey in Fintel’s project development platform in Serbia, either on its own or alongside other large Chinese institutional investors proposed by Windey and approved by Fintel.
Cooperation is focused primarily on the 854-megawatt Maestrale Ring wind farm and other projects in Fintel’s portfolio. These include approximately 110 megawatts of wind capacity currently under construction, including Košava 2, Košava 3, Kula and other projects.
The agreement also allows for joint investment in modular AI data centres located near Fintel’s substations. It makes Windey responsible for providing institutional and state support, including engagement through Chinese diplomatic channels, to speed up permits for Fintel projects. The post-signing announcement called this commitment an “essential part of the agreement.”
Windey, a state-owned Chinese wind turbine manufacturer whose shares are publicly listed and which also invests in the energy sector, was selected as preferred turbine supplier in early 2023 for Košava 2, Kula 2, Ram, Kula 3 and Kula 4. The supply contract covered 28 turbines with a combined capacity of 110 megawatts, as well as a 10-year service and maintenance agreement.
The Windey contract marked the start of implementation of five new green energy projects in Serbia. Fintel’s report lists Košava 2 alongside Kula 2, Kula 3 and Kula 4 among its projects under way, while the partnership agreement also extends to other projects in the company’s portfolio.